MDTA awards $38.6 million contract to remove Key Bridge debris from Patapsco River

The Maryland Transportation Authority approved a deal with Joseph B. Fay Co. to mechanically dismantle the remaining sections of the collapsed bridge starting next month.

By Louis Bennett ·

Illustration for: MDTA awards $38.6 million contract to remove Key Bridge debris from Patapsco River
Illustration generated for this article, not a news photograph.

The Maryland Transportation Authority approved a plan to remove the remaining pieces of the Francis Scott Key Bridge from the Patapsco River.

The authority board voted unanimously on Thursday morning to hire the Pittsburgh-based Joseph B. Fay Co. for the job. The contract is valued at $38.6 million. This figure is below the state's previous projection, which ranged from $50 million to $100 million for the same work.

Preliminary tasks will begin next month. Major demolition work is scheduled to start in January and February. Engineers plan to use mechanical methods rather than explosives to break up the structure. A large excavator mounted on a barge will extend its arm to hammer the residual roadway into rubble. Crews will then scoop the debris into the barge for recycling. Any concrete that falls into the water will be collected by a clamshell dredge.

Jim Harkness, the chief engineer for the MDTA, explained the process in an interview. He said the equipment will effectively poke away at the structure until it breaks apart. The state originally intended to hire Kiewit for the entire rebuild project, including demolition. However, the two parties could not agree on the timeline or the cost earlier this year. Kiewit estimated the total rebuild would cost about $9 billion, while the state's estimate was roughly $5 billion. The initial estimate for the project was $2 billion.

To manage costs and increase competition, the state divided the project into four separate contracts. The demolition work is the first of these contracts to be awarded. The most expensive contract remains for the construction of the new overwater span. That project is worth billions of dollars. The authority is currently reviewing a short list of builders and expects to select a contractor by the summer. The state aims to complete the new bridge by the end of 2030. Harkness noted that the demolition of the old bridge does not interfere with the construction of the new one because the new span will be built slightly southeast of the old location.

Joseph B. Fay Co. will also prepare the foundation for the new bridge. The contractor must clean out sludge from large piles already driven into the riverbed. These piles are 200 feet long and 8 feet in diameter. Crews will use a massive drill to break up the soil inside the piles and then suck out the muck. Harkness compared the process to inserting a giant straw into a milkshake. The company will use the drill to clear the material from the straws.

The authority also launched an interactive online design tool on Thursday. Last month, the agency introduced a progress dashboard for the bridge rebuild. This tool tracks completion percentages for various tasks. For instance, the construction of wooden platforms for rebuilding efforts is currently 100 percent complete.

More News · Baltimore news · Report a business · Got a Story?

Get Baltimore County Herald in your inboxLocal news for Baltimore County, Maryland. Free, a few times a week, unsubscribe any time.

Get Baltimore County Herald in your inboxLocal news for Baltimore County, Maryland. Free, a few times a week, unsubscribe any time.